Bronte Road Safety Initiative

Community-Driven Collaborative Improvement Program

Overview

The Bronte Road Safety Initiative is a collaborative community and local council partnership designed to improve safety across Bronte Road and related pedestrian corridors in the Clovelly precinct.

Project Scope: Bronte Road between St Catherine's School and Murray Street, with focus on related pedestrian intersections affecting school and community facilities.

Quick Facts

4
Local Schools
St Catherine's, Waverley, Clovelly & Bronte Public Schools
1
Aged Care Facility
St Vincent's Aged Care Bronte
Peak Hours
School Times
7:30–9:00am & 2:30–3:30pm
40km/h
Speed Limit
Frequently exceeded

Community Engagement

An organized group of local residents has:

Vulnerable User Groups

This initiative prioritizes the safety of vulnerable users in the area, including:

Project Goal

To establish a collaborative pathway between the community and council that delivers safety improvements reflecting both council priorities and community needs.

Safety Concerns

Key Finding: Significant safety concerns have been identified affecting Bronte Road and related pedestrian corridors during peak hours, particularly when school is in session.

Bronte Road (St Catherine's to Murray Street)

Related Pedestrian Intersections

Leichhardt St / Macpherson St

Key pedestrian crossing between school facilities and residential/commercial areas. High volume of foot traffic during school hours.

Macpherson St / Arden St

Major pedestrian route connecting schools and areas of community interest. Significant student and child movement between these intersections.

Peak Risk Times

Community Directly Affected

This initiative directly impacts a significant residential and business community along Bronte Road. Understanding the scale and composition of affected stakeholders is essential for meaningful community consultation and engagement.

Residential Properties by Location

Summary: Properties directly affected on Bronte Road between Leichhardt Street and Murray Street

Side of Road Address Range Buildings Total Units/Properties
SOUTH SIDE 365A to 329 (E→W) 5 61
NORTH SIDE 364 to 404 (W→E) 2 12
TOTAL 7 73

SOUTH SIDE (Bronte Beach / Ocean) - Southern Footpath (327, 329, 331, 333, 335, 339, 341, 343, 345, 347, 349, 351, 353, 355, 357, 359)

Properties on southern footpath side facing Bronte Beach and coastal areas

337 Bronte Road Building

7+

Residential units

343 Bronte Road Property

Residential property

349 Bronte Road Building

11

Residential units

351 Bronte Road Property

Residential property


NORTH SIDE (Dickson Street Reserve / Inland) - Northern Footpath (364, 364A, 366, 368, 370, 372, 376, 380, 382, 384, 386, 388, 390, 392, 394, 396, 398, 398A, 400, 402, 404)

Properties facing toward Dickson Street Reserve and residential areas

380 Bronte Road Building

11

Residential units

395 Bronte Road Property

1

Residential building

Detailed Unit Information

SOUTH SIDE (365A to 329 - East to West)


South Side - 337 Bronte Road: Multi-unit residential building (7+ units)


South Side - 339 Bronte Road Area: Mixed residential (houses & units, 41 properties)


South Side - 343 Bronte Road: Residential property


South Side - 349 Bronte Road: Multi-unit residential building (11 units)


South Side - 351 Bronte Road: Residential property


NORTH SIDE (364 to 404 - West to East)


North Side - 380 Bronte Road: Multi-unit residential building (11 units)


North Side - 395 Bronte Road: Residential building (1 unit)


Properties Summary

Category Count
Total Buildings/Structures 7
Total Residential Units/Properties 73
South Side Buildings 5
South Side Units/Properties 61
North Side Buildings 2
North Side Units/Properties 12

Community Demographics

The Bronte Road corridor serves a diverse community including:

Local Institutions & Facilities

Key facilities serving the community:

Why Safety Matters Here

The concentration of vulnerable road users (young pedestrians from schools, elderly residents, and recreational users) combined with current traffic conditions makes Bronte Road a priority for community safety improvements. Every resident, worker, and visitor using this corridor deserves a safe environment.

Your Voice Matters

If you live, work, or access services along Bronte Road, we want to hear from you. Your direct experience of traffic conditions, safety concerns, and needs will shape the final recommendations to council. Participate in our consultation process through the "Get Involved" tab or email us your feedback.

Proposed Solutions

The community has identified several potential improvement categories, informed by traffic engineering and urban design expertise:

Traffic Calming

Speed reduction measures on Bronte Road incline, including potential speed limit adjustments, traffic calming devices, and enforcement support.

Crossing Improvements

Enhanced pedestrian crossing facilities at Lugar Street and related intersections, including potential signal optimization and crossing safety enhancements.

Visibility Enhancements

Sightline improvements at the Lugar Street curve and key pedestrian intersections to improve driver awareness and pedestrian safety.

Driveway Safety

Mitigation strategies for high-conflict driveway points, including potential signage, line marking, or geometric modifications.

Existing Council Commitment: Importantly, Waverley Council is already implementing a 40km/h speed limit across the southern LGA (including Bronte Road) in April-June 2025 as part of its Vision Zero safety initiative. The improvements proposed here—speed humps, traffic calming, pedestrian crossings, and clearer signage—directly support and enhance the effectiveness of this already-approved speed limit reduction.
Approach: All proposed solutions will be evidence-based, practical, and developed collaboratively with council to ensure alignment with council standards and strategic objectives.

Implementation Support

The community group is prepared to:

Community Resources

Community Contribution: The initiative is supported by local expertise and organizational resources committed to making this project succeed.

Expertise & Professional Support

Community Commitments

Get Involved

The Bronte Road Safety Initiative welcomes community participation. Here are practical ways you can help make a difference:

📧 Send the Email

Use the Email Template to contact Waverley Council directly. The more voices council hears, the stronger the case for action.

Time required: 5 minutes

👥 Share with Your Network

Share this initiative with neighbors, friends, and family who live or work in the area. Distribute the link to this website through social networks, WhatsApp groups, and neighborhood networks.

Time required: 5-10 minutes

📸 Document Safety Concerns

Take photos or videos of traffic safety issues on Bronte Road—speeding vehicles, near-misses, pedestrians struggling to cross safely. Documentation strengthens the case for council intervention.

Time required: Ongoing, as you notice issues

🗣️ Attend Community Meetings

Participate in community group meetings and council consultations. Your presence shows council that residents care about this issue and supports advocates speaking on behalf of the community.

Time required: 1-2 hours per meeting

📝 Provide Your Story

Share personal experiences with traffic safety concerns on Bronte Road. Real stories from residents and parents are powerful evidence for why council should prioritize this area.

Time required: 10-15 minutes to write

💬 Engage with Council

Attend council meetings when road safety or traffic matters are discussed. Speak during public comment periods if available. Subscribe to council updates to stay informed about progress.

Time required: Variable, depending on council meeting schedule

🤝 Spread the Word at Schools

If you have connections with St Catherine's, Waverley, Clovelly or Bronte Public Schools, encourage them to communicate safety concerns to parents. Schools have a vested interest in pedestrian safety.

Time required: 10-20 minutes to connect


Make Your Voice Count

Remember: Council responds to community engagement. The more residents who submit feedback, attend meetings, and document concerns, the stronger the case for action becomes. Even small contributions add up—every email, every shared story, every attendee at a meeting strengthens the initiative.

Newsletter Information

Subscribers will receive:

  • Monthly updates on initiative progress
  • Announcements of community consultation events
  • Council meeting dates and opportunities to engage
  • Fundraising and volunteer opportunities (if applicable)
  • Success stories and wins for the initiative

We respect your privacy. You can unsubscribe at any time. We will never share your email with third parties.

Engagement Methodology

The Bronte Road Safety Initiative will follow a proven community engagement model aligned with Waverley Council's approach to streetscape consultation, as successfully demonstrated in the Miller Street Upgrade project.

Reference Document: Miller Street Upgrade Consultation Report - Stage Two (July 2024) — Full official consultation report showing community feedback, engagement methods, and final recommendations.

Framework: IAP2 Community Engagement Model

Like Waverley Council, we will use the adapted IAP2 (International Association for Public Participation) model, which includes:


Multi-Channel Engagement Strategy

Drawing from Miller Street's successful consultation (which achieved 82% support from 48 submissions), we will use multiple engagement pathways to reach diverse community members:

📱 Online Have Your Say Survey

Channel: Dedicated Waverley Council "Have Your Say" project page

What it does: Gathers structured feedback on key issues and design preferences

Miller Street result: 47 survey submissions from 352 visitors

Timeline: Ongoing during consultation phases

📬 Flyer Distribution

Channel: Direct mail to nearby properties and businesses

What it does: Notifies residents and encourages participation

Miller Street coverage: ~653 properties/businesses reached

Timeline: Beginning of each consultation phase

📱 Social Media

Channels: Facebook & Instagram

What it does: Promotes consultation, shares updates, encourages engagement

Miller Street reach: 1,528 (Facebook), 750 (Instagram)

Timeline: Throughout consultation period

📧 Newsletter Updates

Channels: Waverley Weekly, Have Your Say e-newsletter

What it does: Keeps engaged community members informed

Miller Street reach: 9,372 e-newsletter recipients

Timeline: Monthly updates during consultation

👥 Pop-Up Consultations

Format: In-person community engagement days

What it does: Enables face-to-face discussion with residents and families

Miller Street approach: Wednesday afternoon sessions, flexible dates

Timeline: During Phase 2 of the initiative

☎️ Phone & Email Feedback

Channel: Direct contact with project manager

What it does: Allows individual concerns and detailed feedback

Miller Street result: 1 detailed phone consultation with follow-up

Timeline: Ongoing availability

🏫 Stakeholder Outreach

Targets: Schools, childcare, aged care, local businesses

What it does: Engages organizations with direct interest in pedestrian safety

Miller Street approach: Direct outreach to kindergarten, churches, precincts

Timeline: Early engagement in Phase 1

📊 Council Website & Documentation

Content: Project information, design options, consultation reports

What it does: Provides transparent information and tracks progress

Miller Street transparency: Full consultation report made public

Timeline: Updated throughout project


Consultation Phases & Timeline

Phase 1: Initial Council Meeting & Community Notification

Duration: 4-6 weeks
Activities:

  • Present proposal to council's traffic and planning teams
  • Notify community of initiative via flyer distribution
  • Launch Have Your Say webpage
  • Begin stakeholder outreach to schools, aged care, businesses

Expected outcome: Council agreement to collaborate; initial community awareness

Phase 2: Community Consultation & Design Feedback

Duration: 6-8 weeks
Activities:

  • Online Have Your Say survey (similar to Miller Street model)
  • Pop-up consultation events in the community
  • Social media and newsletter updates
  • Stakeholder meetings with schools and organizations
  • Phone/email feedback collection

Expected outcome: 40-50+ community submissions; clear design preferences; documented feedback

Phase 3: Design Development & Consultation Report

Duration: 4-6 weeks
Activities:

  • Compile and analyze community feedback
  • Develop detailed consultation report (like Miller Street Stage Two report)
  • Refine designs based on community input
  • Address specific concerns raised (drainage, visibility, parking, etc.)

Expected outcome: Comprehensive consultation report; refined design options; council presentation


Success Metrics: Miller Street Model

The Bronte Road initiative can expect similar engagement patterns to Miller Street's successful consultation:

Survey Submissions

Miller Street: 47 submissions
Target for Bronte Road: 40-60 submissions from a larger catchment

Support Rate

Miller Street: 82% in favor
Expected for Bronte Road: Similar or higher (more urgent safety issue)

Website Engagement

Miller Street: 473 page visits
Target for Bronte Road: 500+ visits (higher awareness)

Social Media Reach

Miller Street: 1,528 (Facebook), 750 (Instagram)
Goal for Bronte Road: Broader reach through community sharing

Newsletter Reach

Miller Street: 9,372 recipients
Via Waverley Council: Reaches entire LGA interested in updates

Response Demographics

Miller Street: 44% female, 41% male, 9% non-binary
Age range: Broad representation (under 20 to 70+)


Community Feedback Integration

Following Waverley's approach, community feedback will be:

Transparency Commitment: Like Miller Street's publicly available consultation report, the Bronte Road initiative will publish a comprehensive Stage Two consultation report showing all feedback received and how community input shaped the final design recommendations presented to council.

Frequently Asked Questions

Why is this urgent?

Bronte Road's combination of speeding vehicles, poor sightlines, and high pedestrian traffic during school hours creates a genuine safety risk. With four schools in the area and an aged care facility, vulnerable populations use this route daily. The longer we wait, the greater the risk of a serious incident.

What if I don't live on Bronte Road?

Everyone is welcome to participate. If you use the area (work nearby, pass through, have children at local schools, visit aged care residents), your voice matters. Safety improvements benefit the entire community.

How long will implementation take?

The timeline depends on council priorities and budget. Based on similar projects like Miller Street, the process typically takes 12-24 months from initial meeting to completion of implementation. We've designed our approach to be efficient while ensuring thorough community consultation.

Will this cost residents money?

No. This is a council infrastructure project funded by council and Australian Government grants. Residents don't pay for implementation—you simply help advocate for it.

What if council says no?

Council feedback will help us understand their concerns and constraints. Even if initial proposals are declined, the process builds the case for future action. Sustained community pressure, combined with incident documentation, often leads to eventual approval.

Can I help but don't want to be publicly identified?

Yes. You can send the email template from your personal email account, provide anonymous documentation, or support privately. All contributions are valuable.

Who's behind this initiative?

This is a grassroots community initiative started by local residents concerned about safety. We've engaged traffic engineers and urban design professionals who are donating expertise. We're not affiliated with any political party—our focus is purely on community safety.

How can I stay updated on progress?

Follow updates through this website, contact the community group leads, or subscribe to Waverley Council's notification system for road and traffic updates at www.waverley.nsw.gov.au.

What makes this different from previous safety requests?

This initiative combines specific, evidence-based safety concerns with community signatures, professional expertise, and a clear collaborative proposal to council. We're not just raising complaints—we're offering to be partners in solutions.

Can I suggest additional safety improvements?

Absolutely. Community input drives the design process. Share your ideas when you send the email to council, or engage during consultation phases. The more comprehensive our understanding of community needs, the better the final solutions.

Contacts

The following individuals and representatives have been or will be contacted regarding the Bronte Road Safety Initiative. These are the key decision-makers and community liaisons who can champion pedestrian safety improvements for Bronte Road.

Will Nemesh

Will Nemesh

Position: Mayor
Party: Liberal Party of Australia
● Responded
Katherine Westwood

Katherine Westwood

Party: Liberal Party of Australia
● Responded
Lauren Townsend

Lauren Townsend

Party: Liberal Party of Australia
● Responded
Paula Masselos

Paula Masselos

Party: Australian Labor Party
● No response

Herbert Lam

Position: Project Manager Civil Infrastructure
Organization: Waverley Council
Email: majorprojects@waverley.nsw.gov.au

◐ Not yet contacted

The Beast Magazine

Focus: Local news, community stories, Eastern Suburbs coverage
Website: thebeast.com.au
Email: info@thebeast.com.au

Community media outlet reaching local residents and families in the Eastern Suburbs. Excellent channel for raising awareness about Bronte Road safety within the community.

● Responded

Email Template for Community Members

Fill in your details below, then copy the email content and send it from your own email account to Waverley Council:


All Bronte Road Properties in Area (Sorted by Address Number)

South Side (Southern Footpath - Numbers: 327, 329, 331, 333, 335, 339, 341, 343, 345, 347, 349, 351, 353, 355, 357, 359):
Major properties: 337 Bronte Road (7+ units), 339 Bronte Road (41 properties), 349 Bronte Road (11 units)
Subtotal: Individual properties spanning 327-359

North Side (Northern Footpath - Numbers: 364, 364A, 366, 368, 370, 372, 376, 380, 382, 384, 386, 388, 390, 392, 394, 396, 398, 398A, 400, 402, 404):
Major properties: 380 Bronte Road (11 units), 395 Bronte Road (1 building)
Subtotal: Individual properties spanning 364-404

Other Addresses (Outside consultation area):
414 Bronte Road, 422 Bronte Road, 424 Bronte Road, 428-430 Bronte Road (5+ units), 440 Bronte Road, 445 Bronte Road, 471 Bronte Road, 499 Bronte Road

Total Documented: 40+ individual property numbers, multiple buildings with units

Project Timeline

The Bronte Road Safety Initiative follows a collaborative, phased approach aligned with Waverley Council's Road Infrastructure Renewal Program and strategic initiatives. This timeline demonstrates how the initiative integrates with Council's broader commitment to improving road safety and pedestrian accessibility across the LGA.

Alignment with Council Programs: This timeline is designed to align with Waverley Council's Road Infrastructure Renewal Program 2024-2025 and reflects the collaborative approach successfully used in projects like the Miller Street Upgrade.

Phase 1: Initial Meeting with Council

Timeframe: Next 4–6 weeks (flexible)
Objective: Present community findings, discuss council's risk assessment, and establish collaborative pathway

Phase 2: Collaborative Assessment

Timeframe: 6–8 weeks
Objective: Joint council-community review of safety concerns, validation of findings, and exploration of feasible solutions. Council traffic engineers inspect site and validate community observations.

Phase 3: Solution Design

Timeframe: 8–12 weeks
Objective: Development of detailed improvement options with engineering and design input; cost and feasibility analysis. Multiple design options prepared for community feedback.

Phase 4: Community & Stakeholder Consultation

Timeframe: 6–10 weeks (concurrent with design refinement)
Objective: Gather feedback from residents, schools, aged care facilities, and other stakeholders; refine solutions based on input. Similar to Miller Street (47 submissions, 82% support).

Phase 5: Council Decision & Implementation Planning

Timeframe: 4–8 weeks
Objective: Council evaluation and decision on approved measures; development of implementation timeline and budget. Preparation of business case for funding applications.

Phase 6: Implementation & Monitoring

Timeframe: 12–18 months (based on Bourke Street project)
Objective: Execute approved safety improvements; monitor effectiveness and gather ongoing community feedback. Based on similar council projects, this phase includes detailed design finalization, procurement, and construction.

Total Expected Timeline: Based on similar Waverley Council projects (Bourke Street: 2.5 years, Miller Street: ongoing with similar phases), the Bronte Road Safety Initiative can expect approximately 18–30 months from initial council meeting to completion. This includes: Initial meeting + assessment (4–6 weeks) + design (8–12 weeks) + consultation (6–10 weeks) + council decision (4–8 weeks) + implementation (12–18 months).

Note: The 40km/h speed limit for Bronte Road is already being implemented April-June 2025 as part of Waverley Council's existing Vision Zero initiative. The Bronte Road Safety Initiative timeline focuses on securing the additional traffic calming infrastructure (speed humps, pedestrian crossings, visibility enhancements) that will complement this approved speed limit reduction.

Flexibility: The community is flexible with timing and location for the initial meeting with council. We are ready to accommodate council's schedule and preferences.

Next Step

Confirmation of initial meeting with council's traffic and planning teams to review this proposal and establish collaborative framework.


Alignment with Council Processes

This timeline reflects how the Bronte Road Safety Initiative integrates with Waverley Council's established project delivery processes:

For more information on related Council programs, see the Related Information tab.